Thursday 30 January 2014

Week 24 and 25


Most windows are in now. Bays windows are waiting for engineering specs and the dorma windows will go in once we have a mobile scaffold to reach them from inside.


A team of bricklayers start next week to get us closer to lock up. They won't finish next week but hopefully they'll be able to get us a long way.


 Some internal views. Once we get bricked up we can start on the inside.

Friday 17 January 2014

Week 20 -23


Things slowed as expected over the Christmas break. Carpenters worked hard to get the frame finished, braced and tied down before Christmas.


The roofers came in for hell week when the temperatures were 40 degrees plus all week. Thursday and Friday peaked at 44 degrees.


They finished Saturday. Now windows will start going in.